Repeating tasks only show on Day view
I have a repeating task for every Thursday. I discovered recently that repeating tasks only shows up on the Day view--it doesn't appear in the Week or the Month view. I have missed this repeating task for multiple weeks now since I usually use the Week view (it's just more convenient for me to see the week as a whole). Can you please advise whether repeating tasks can appear on all views and not just the Day view?
Completed
You may have turned off the visibility in the repeat settings, can you check? Go to the task, click the repeat icon and look at 'Edit Calendar Visibility' If it's not that, it could be a misunderstanding in how task repeaters work (they repeat when complete)